Final rule published
Drawbridge Operation Regulation; Wishkah River, Aberdeen, WA
Record date · Nov 6, 2026
What this means
- Status
- Final rule published
- What happened
- The Coast Guard is changing the operating schedule that governs the Puget Sound and Pacific railroad bridge (PS&P) across the Wishkah River, mile 0.1 in Aberdeen, WA. This rule will change the PS&P railroad bridge draw position to the fully closed-to-navigation position. Furthermore, this rule requires 24-hour notice for all drawbridge openings and a bridge operator will no longer be required to be on site.
- What to check next
- The published rule gives Dec 7, 2026 as its effective date. Check the official docket for later changes.
Record details
- Federal Register document
- 2026-22677
- Stated effective date
- 2026-12-07
Sources and related records